Commercial Permitting in DFW: Fees & Timelines
How commercial permitting works across DFW cities — and how to keep it from stalling your project.
Commercial permitting in Dallas–Fort Worth varies by city, but plan review typically takes a few weeks to a few months, and building-permit fees are usually a percentage of construction valuation plus plan-review and impact fees. The biggest schedule risk is plan-review comments and resubmittals — which is where active expediting pays off.
Typical permitting timelines & fees in DFW
| Item | Typical |
|---|---|
| Commercial plan review | ~3–12 weeks (by city & size) |
| Building permit fee | a % of construction valuation |
| Plan-review fee | a % of the permit fee |
| Impact / utility fees | vary by city & use |
| Expediting / management | scoped per project |
Timelines and fees vary by municipality — Dallas, Fort Worth, Arlington, Irving, Plano and Richardson each differ.
Who pulls the permit?
On a commercial project, the general contractor typically pulls and holds the building permit and is responsible for inspections and code compliance through certificate of occupancy. As your contractor we manage that entire process so you don't have to navigate the city yourself.
What keeps permitting on schedule
- Complete submittals — fewer review comments up front
- Fast comment response — quick resubmittals
- City relationships — knowing each municipality's process
- Inspection coordination — scheduling to avoid gaps
- Code review — catching issues before the city does
See our permits & inspections service for what's included.